Feasibility study of geothermal utilization of Yangbajain field in Tibet autonomous region, P.R. China

Skoða fulla færslu

Titill: Feasibility study of geothermal utilization of Yangbajain field in Tibet autonomous region, P.R. ChinaFeasibility study of geothermal utilization of Yangbajain field in Tibet autonomous region, P.R. China
Höfundur: Caixia, Sun 1980 ; Jarðhitaskóli Háskóla Sameinuðu þjóðanna
URI: http://hdl.handle.net/10802/12774
Útgefandi: United Nations University, Orkustofnun
Útgáfa: 12.2008
Ritröð: United Nations University., UNU Geothermal Training Programme, Iceland. Report ; 2008:3
Efnisorð: Meistaraprófsritgerðir; Jarðhiti; Jarðhitarannsóknir; Jarðfræði; Fjarhitun; Endurnýjanleg orka; Tíbet
ISSN: 1670-7427
ISBN: 9789979682493 (ób.)
Tungumál: Enska
Tengd vefsíðuslóð: http://www.os.is/gogn/unu-gtp-report/UNU-GTP-2008-03.pdf
Tegund: Bók
Gegnir ID: 991007672969706886
Athugasemdir: Lokaritgerð (MS) við Háskóla ÍslandsMyndefni: kort, línurit, töflur
Útdráttur: This study investigates the feasibility of the renewable energy utilization in Tibet, which is known as the “world roof” with highest elevation and splendid natural scenery. Based on the available energy assessment and market analysis, a technical and economic feasibility study is carried out on geothermal utilization of Yangbajain field with the objective of solving both electricity shortage and lack of space heating so as to improve the Tibetan people’s living condition. The technical feasibility study is to set up thermodynamic model of proposed different power generation scenarios and long distance district heating system to analyze and optimize each scenario by using EES and Matlab programmes. Four alternative scenarios optimized for new power plant design are double flash cycle (Scenario 1), hybrid single flash and ORC cycle with isopentane as working fluid (Scenario 2), pure ORC cycle with isobutane as working fluid (Scenario 3), and hybrid single flash and Kalina cycle (Scenario 4). The conceptual design of district heating system with about 90km distance from Yangbajain to Lhasa is as well carried out. The results indicate that all power cycles are technically feasible at different efficiency and heating system can be put up under appropriate design and construction. A financial viability evaluation is performed for all scenarios using engineering economic Present Worth (PW) value analysis method with objective to figure ....